Hayat Mall
60 Days
Full Store Renovation: 1- Demolition Works. 2- Site Preparation. 3- Renovation Works. 4- Site Handover.
Full Store Renovation including:
A- Demolition:
1- Removal of existing Walls and Glass.
2- Removal of existing furniture and service counters.
3- Removal of existing tiles and ceiling.
4- Removal of existing sewage pipes.
5- Removal of existing lighting.
6- Removal of all machinery in site including (Coffee Machines, Toasters, Grills, Display Cabinets, Freezers, Counters, etc...)
7- Removal of Bulkhead and logos.
B- Site Preparation:
1- Install Hoarding.
2- Ensure Safety Measures and mall visitor's passage around the store.
3- Closing and securing HVAC + FF/FA systems.
4- Disconnecting Electric wires from main cabinet to store.
5- Installing temporary Electric supply for site works only.
C- Renovation phase:
1- Install new walls as per new design.
2- Install new columns and bulkheads as per new dimensions.
3- Floor leveling and installations of new parquet tiles.
4- Install new electrical wires as per the new electrical plan.
5- Manufacturing new furniture as per the new concept design.
6- Apply Paint works.
7- New Lighting.
8- New Wooden Counters Oak Finish, Wooden Displays Matt Brown Finish, Wooden Cabinets Oak Finish, Stainless steel preparation tables, Stainless Steel with Marble top Food Preparation Counter.
9- Logo Works.
10- Decoration Works.
D- Site Handover:
1- Removal of Hoarding.
2- Site Deep Cleaning.
3- Commissioning and Testing.
4- Getting Mall Approvals.
5- Paint retouch for all wooden works and walls where needed.
6- Site Soft Opening.
7- Site rechecking and confirming no snags.
8- Site Grand Opening.