Cenomi - Hamra Mall - 2nd floor
65 Days
Key Turn Project! 1- Civil Works 2- Architectural Works 3- MEP Works 4- Furniture
Shop Name: Z Games.
Location: Hamra Mall.
Shop Size: 188m2.
City: Riyadh, Saudi Arabia.
Scope of Work:
A- Civil & Architectural Works:
1- Demolition Works.
2- Flooring Works.
3- Partition & Wall Works.
4- Ceiling Works.
5- Painting Works.
6- Shopfront.
7- Furniture Works.
8- CCTV.
9- Signage Works.
10- 65" LED Displays.
11- Security Gates.
B- MEP Works:
1- HVAC Works.
2- Firefighting & Fire-alarm works.
3- Electrical Engineering Works.
Material Details:
1- Double walls Gypsum board “fire-rated” for all partition & ceiling works, including rockwool 128gsm isolation “fire-rated” and closing all wall holes with fire-rated compound mix.
2- 60x60 Tiles including metal framing and joints for all floor works, along with natural marble for the control zone as per mall requirements.
3- Jotun paints for all painting works.
4- MDF 18mm wood material for shopfront, powder coated.
5- Aluminum shutter door with transparent polycarbonate slaps.
6- Acrylic signages with embedded LED lighting.
7- MDF Furniture with embedded LED lighting for each shelf.
8- LED Strip light for shop ceiling and shopfront.
9- 5 Tons LG concealed Air Conditioning compressors with stainless steel ducting & isolation.
10- 4mm electric wiring across all shop with under floor PVC pipes & aluminum isolated cables for ceiling and wall electrical works.
11- 3 phase Schneider electrical board with 60A circuit breaker.
12- 24 concealed Firefighting sprinklers below & above ceiling.
13- FACP & smoke detectors for Fire alarm system.
C- Furniture Works:
1- Cashier Counter.
2- Wall Displays.
3- Counter Displays.
4- Shelves & Cabinets.
5- Stock Room Cabinets.